The contract price may change under the following circumstances.Â
PAYMENT 1: Home owners warranty prior to excavation.
PAYMENT 2: Due upon delivery of steel bars and excavation by Builder or Customer on completion.
PAYMENT 3: Due on day of steel fixing completion.
PAYMENT 4: Due prior to laying tiles, equipment delivery & Interior. Make payment when tiles arrive on site & ready to book finishing trades. Shell finishes carried out once coping on site & pool fence erected.
PAYMENT 5: Due on day of Interior lining to book handover. Final O.C. is Customer responsibility and does not delay final payment.
Contract and variation payments are due on the day by 4 pm. No invoices are sent.
You follow progress payments as per your written contract and any variations.
Do not commence construction if your finances are not in place and cleared funds.
NOTE: No changes will be made after mark out.
If Customer has nominated excavation, follow these guidelines;
Customer to provide the correct size material to suit this nominated coping width and will allow for a 50mm overhang which will provide the right aesthetics for your interior lining to come up the wall and finish underside. Pools that are out of ground will be left with bare concrete on the outside of the shell. This is called a riser. If planning to tile or render an external riser, allow for tile overhang to suit when choosing your material inside overhang to and outside of pool shell. No external wall or coping riser finishes are included and are to be dressed according to your landscape plans.Â
Customer to provide tiles on a dot system and not mesh backing. Mesh is known to loosen.
Interiors are hand trowelled and lightly exposed. Some products come pre-mixed and some are custom mixed. For coloured finishes the maintenance is higher & water chemistry must be kept perfectly logged. Water colours shown on www.bluehaven.com.au.
BLUE HAVEN TASK:
1A. Contracted Excavation – Blue Metal, Pier Cylinders & Steel delivery or markout for owner excavation.
1B. Steel & Plumbing – Plumbing lines and light conduit is laid. Local government inspections for steel & piering.
1C. Concreting – Builders rubble will only be disposed of in a construction waste bin provided by owner.
2A. Water Feature – Any water features will be sculpted before coping materials are laid. (FACT SHEET 9 *)
2B. Tiling, Edging & Paving – Tiling, edging, paving or waterfall blade installation.
3A. Plumbing Lines – Plumbing lines completed to equipment room or area of desired location.
3B. Equipment Installation –Equipment delivered and installed. (FACT SHEET 13 *)
5A. Permanent Fencing & Equipment Enclosure – Contact Rep if you require a quote for fence installation.
5B. Fence Inspection –Fence inspection booked with certifier or council.
6A. Pool Clean & Sealing – Sealing of wet concrete weepers and all pipes waterproofed.
6B. Interior Lining –Interior lining, acid cleaning of surface and fitting of internal dress fittings.
7. Pool Filling – Pool is filled. (Note: Water is green and will be clear when filtration running) Payment 5 is due.
8. Handover – Rep to demonstrate the pool equipment and assist in any questions. (FACT SHEET 15 & 21 *)
8B. Site Clean Up – Blue Haven to clear area around pool.
13. Salt / Minerals – Up to 6 weeks after handover delivery of salt / minerals & PH Doser Calibration.
CLIENT OBLIGATION:
1A. Temporary Fencing – Temp Fence installation. DIY owner excavation or access via neighbour. Waiver now due.
Waiver form now due. Skip Bin (2 cubic metre).
Tipping fee is now due. (CASH ONLY FOR SOIL REMOVAL.)
1B. Pool height, shape, location, filtration position signed off by both parties. Payments 2 & 3 Due.Â
1C. Water concrete shell for the 5 days. 10 mins AM & 10 mins PM.
2A. Delivery of tiles, paving & waterfall blade, ask your Blue Haven Rep for Specs / assist. (FACT SHEET 17 *)
2B. Prior to the laying of tiles, Payment 4 is now due.
3A. Filtration location to be advised. (Additional $ for pipes over 12m from pool) (FACT SHEET 13 *)
3B. Slab (or hard base) needs to be completed. Post to mount chlorinator.
4A. Power and lights installed and pool to be earthed by a licenced electrican.
Please contact your Rep if you require assistance with Power installation. (FACT SHEET 16 *)
4B. If you have a gas heater, gas line installation is required by a licenced gas fitter.
Please contact your Rep if you require assistance with Gas installation. (FACT SHEET 16 *)
5A. Compliant fence to be installed before interior work done. (FACT SHEET 12 *)
5B. Resuscitation chart to be erected on fence or filtration enclosure now due. (FACT SHEET 13 *)Â
6A. Pool to be dewatered and clear of all building debris. (FACT SHEET 19 *)
6B. Lights, and hydro bowl to be provided on site. Please hand to applicator.
8.We require 1 hour of your time for your instruction on pool ownership.
8B.We require a skip bin for clean-up. From start of job or before handover.
9. We require a skip bin for clean-up. From start of job or before handover.
Relocate any items or structures to clear of the 900mm no climb zone. (FACT SHEET 12 *)
10. Now is the time to organise your pool landscaping. (FACT SHEET 20 *)
11. Final Occupation Certificate – Local government final inspection.
12. Landscaping – Blue Haven have packages available to assist you. Ask your Rep for more information.
13. Salt or mineral order and delivery.
Note: Do not put into the pool water until instructed. https://bluehaven.com.au/guides-insights/fact-sheets/
MORE INFORMATION:
The following is additional information relating to the timeline. The completion of these items on time will ensure
your pool project is on schedule from the start of excavation to the filling of water and final signoff.
1A. A compliant fence required to protect the excavation void and will need to remain in place to fill the pool with water at end of the build.
During the entire project we require clear access in and around the pool, in order to complete the project.
Fair access must be provided for our material and machinery; this may be through your garage or up your driveway or via a neighbouring property. Our tradesmen will be on site early so please arrange to move your vehicles in advance of our arrival. Difficulty in access will require additional labour to get machinery and materials on site and could incur an additional charge.
Should you have pets please arrange to have them tied up or kennelled away from the work site and any droppings removed prior as we will have various items such as tarps and hoses running across the area.
Every attempt will be made to keep the site and surrounds clean and free of rubbish, however it is a building site and some temporary markings will occur, and it must be understood that we will be working with cement etc., so we require a position on site to clean our equipment as the setting time of the material means this cannot be done off site.
1B. Local government inspections required for steel & piering. If you are the owner applicant, this is your responsibility. Note: some Certifiers require an Engineer Certificate. It is advised to check conditions of approval.
Filtration final position to be confirmed as lines are run at this stage to final location.
1C. Concrete wash out is common to empty the hopper. Blobs are spread out as smaller rubble to handle when dry & disposed of in a suitable construction bin provided by owner.
2A. You are to provide correct size material to suit nominated coping width, allow for 50mm overhang into pool.
Oversize material will not be cut on site. Tiles must be on dot backing, not mesh. Tiles, glue & grout to be
supplied by customer.
2B. Sand & cement used to fill in pavers. Special coloured grouts to be supplied by client if desired. The coping
and waterline tiles must be finished and grouted with any expansion joints filled and all items cleaned off. External
surrounds laid by 3rd party must comply with adequate expansion joint and not butt up to pool structure.
3B. Electrician to earth the pool, install black light cable and any extensions if required, provide outdoor double power point 12 amp, occasional 3 phase power requirements for large heat pump or pool pumps.
The filtration will need to be in place and operational. We do provide precast slabs for the equipment to sit on however most Customers choose to provide a slab area for the filtration to on as part of their overall landscaping vision. You should allow 1100mm x 1100mm which is adequate for standard gear consisting of the filter, sanitiser and up to 2 pumps.Â
Order your permanent enclosure after equipment installation to ensure the right size.
4A. Pool to be earthed by your electrician. An outdoor waterproof power point to be supplied (12 amp double). Electrician to pull through black cable to connect the transformer. Lights and transformer to be on site.
5A. A compliant fence required to fill the pool with water. Pool filtration to be enclosed as per local government specs. Boundary fences to be raised to 1.8m if using as a pool safety barrier and items to be cleared of the 900mm non climb zone.
5B. If a permanent fence is erected, the temporary fence can now be dehired and removed from the site.
6A. The colour of your interior lining is as per contract. Any variations must be agreed in writing before materials arrive. If you would like to see images of your pool water colour in advance to make any changes.
The pool must now be clean and dewatered by you.
6B. Any of the lights or other internal fittings that need to be in screwed in place should be done in advance. All lights must be on site and provided to the render crew to render into place.
An uninterrupted supply of clean water and 240V power need to be available within 30 meters of the pool.
If your property has trees surrounding your pool that may drop leaves, flowers and nuts; please ensure these do not drop onto the pool floor before it is filled as they can cause tannin staining. We will leave the pool surface spotless but will not be responsible for organic droppings once we are finished and or leave the site. If necessary we suggest you cover the pool with a cheap tarp to keep leaves etc. off until the
pool is filled and until the surface is cured.
Cleaning of glass fencing, whilst we will do our utmost to work cleanly we do not accept liability, please ensure that the fence is completely covered/masked in advance to prevent any splashing onto the glass.
Note: While every effort will be made, and we do clean up after we finish, we are not commercial cleaners.
7. As the pool requires filling on the day immediately the render is finished. This means once your interior is done and pool filled the handover will be locked in. Your final payment will be due when the pool is full of water, prior to handover.
If there is anything preventing the immediate payment upon water filling please discuss this with your Rep. as its important for the water to not go stagnant once filled and this may happen is matters are left to be
addressed at this final stage.
8B. We require a skip bin for site clean up provided by you and will load it as part of our service.
The contract price may change under the following circumstances.Â
PAYMENT 1: Home owners warranty prior to excavation.
PAYMENT 2: Due upon delivery of steel bars and excavation by Builder or Customer on completion.
PAYMENT 3: Due on day of steel fixing completion.
PAYMENT 4: Due prior to laying tiles, equipment delivery & Interior. Make payment when tiles arrive on site & ready to book finishing trades. Shell finishes carried out once coping on site & pool fence erected.
PAYMENT 5: Due on day of Interior lining to book handover. Final O.C. is Customer responsibility and does not delay final payment.
Contract and variation payments are due on the day by 4 pm. No invoices are sent.
You follow progress payments as per your written contract and any variations.
Do not commence construction if your finances are not in place and cleared funds.
NOTE: No changes will be made after mark out.
If Customer has nominated excavation, follow these guidelines;
The contract price may change under the following circumstances.Â
PAYMENT 1: Home owners warranty prior to excavation.
PAYMENT 2: Due upon delivery of steel bars and excavation by Builder or Customer on completion.
PAYMENT 3: Due on day of steel fixing completion.
PAYMENT 4: Due prior to laying tiles, equipment delivery & Interior. Make payment when tiles arrive on site & ready to book finishing trades. Shell finishes carried out once coping on site & pool fence erected.
PAYMENT 5: Due on day of Interior lining to book handover. Final O.C. is Customer responsibility and does not delay final payment.
Contract and variation payments are due on the day by 4 pm. No invoices are sent.
You follow progress payments as per your written contract and any variations.
Do not commence construction if your finances are not in place and cleared funds.
NOTE: No changes will be made after mark out.
If Customer has nominated excavation, follow these guidelines;
Customer to provide the correct size material to suit this nominated coping width and will allow for a 50mm overhang which will provide the right aesthetics for your interior lining to come up the wall and finish underside. Pools that are out of ground will be left with bare concrete on the outside of the shell. This is called a riser. If planning to tile or render an external riser, allow for tile overhang to suit when choosing your material inside overhang to and outside of pool shell. No external wall or coping riser finishes are included and are to be dressed according to your landscape plans.Â
Customer to provide tiles on a dot system and not mesh backing. Mesh is known to loosen.
Interiors are hand trowelled and lightly exposed. Some products come pre-mixed and some are custom mixed. For coloured finishes the maintenance is higher & water chemistry must be kept perfectly logged. Water colours shown on www.bluehaven.com.au.
BLUE HAVEN TASK:
1A. Contracted Excavation – Blue Metal, Pier Cylinders & Steel delivery or markout for owner excavation.
1B. Steel & Plumbing – Plumbing lines and light conduit is laid. Local government inspections for steel & piering.
1C. Concreting – Builders rubble will only be disposed of in a construction waste bin provided by owner.
2A. Water Feature – Any water features will be sculpted before coping materials are laid. (FACT SHEET 9 *)
2B. Tiling, Edging & Paving – Tiling, edging, paving or waterfall blade installation.
3A. Plumbing Lines – Plumbing lines completed to equipment room or area of desired location.
3B. Equipment Installation –Equipment delivered and installed. (FACT SHEET 13 *)
5A. Permanent Fencing & Equipment Enclosure – Contact Rep if you require a quote for fence installation.
5B. Fence Inspection –Fence inspection booked with certifier or council.
6A. Pool Clean & Sealing – Sealing of wet concrete weepers and all pipes waterproofed.
6B. Interior Lining –Interior lining, acid cleaning of surface and fitting of internal dress fittings.
7. Pool Filling – Pool is filled. (Note: Water is green and will be clear when filtration running) Payment 5 is due.
8. Handover – Rep to demonstrate the pool equipment and assist in any questions. (FACT SHEET 15 & 21 *)
8B. Site Clean Up – Blue Haven to clear area around pool.
13. Salt / Minerals – Up to 6 weeks after handover delivery of salt / minerals & PH Doser Calibration.
CLIENT OBLIGATION:
1A. Temporary Fencing – Temp Fence installation. DIY owner excavation or access via neighbour. Waiver now due.
Waiver form now due. Skip Bin (2 cubic metre).
Tipping fee is now due. (CASH ONLY FOR SOIL REMOVAL.)
1B. Pool height, shape, location, filtration position signed off by both parties. Payments 2 & 3 Due.Â
1C. Water concrete shell for the 5 days. 10 mins AM & 10 mins PM.
2A. Delivery of tiles, paving & waterfall blade, ask your Blue Haven Rep for Specs / assist. (FACT SHEET 17 *)
2B. Prior to the laying of tiles, Payment 4 is now due.
3A. Filtration location to be advised. (Additional $ for pipes over 12m from pool) (FACT SHEET 13 *)
3B. Slab (or hard base) needs to be completed. Post to mount chlorinator.
4A. Power and lights installed and pool to be earthed by a licenced electrican.
Please contact your Rep if you require assistance with Power installation. (FACT SHEET 16 *)
4B. If you have a gas heater, gas line installation is required by a licenced gas fitter.
Please contact your Rep if you require assistance with Gas installation. (FACT SHEET 16 *)
5A. Compliant fence to be installed before interior work done. (FACT SHEET 12 *)
5B. Resuscitation chart to be erected on fence or filtration enclosure now due. (FACT SHEET 13 *)Â
6A. Pool to be dewatered and clear of all building debris. (FACT SHEET 19 *)
6B. Lights, and hydro bowl to be provided on site. Please hand to applicator.
8.We require 1 hour of your time for your instruction on pool ownership.
8B.We require a skip bin for clean-up. From start of job or before handover.
9. We require a skip bin for clean-up. From start of job or before handover.
Relocate any items or structures to clear of the 900mm no climb zone. (FACT SHEET 12 *)
10. Now is the time to organise your pool landscaping. (FACT SHEET 20 *)
11. Final Occupation Certificate – Local government final inspection.
12. Landscaping – Blue Haven have packages available to assist you. Ask your Rep for more information.
13. Salt or mineral order and delivery.
Note: Do not put into the pool water until instructed. https://bluehaven.com.au/guides-insights/fact-sheets/
MORE INFORMATION:
The following is additional information relating to the timeline. The completion of these items on time will ensure
your pool project is on schedule from the start of excavation to the filling of water and final signoff.
1A. A compliant fence required to protect the excavation void and will need to remain in place to fill the pool with water at end of the build.
During the entire project we require clear access in and around the pool, in order to complete the project.
Fair access must be provided for our material and machinery; this may be through your garage or up your driveway or via a neighbouring property. Our tradesmen will be on site early so please arrange to move your vehicles in advance of our arrival. Difficulty in access will require additional labour to get machinery and materials on site and could incur an additional charge.
Should you have pets please arrange to have them tied up or kennelled away from the work site and any droppings removed prior as we will have various items such as tarps and hoses running across the area.
Every attempt will be made to keep the site and surrounds clean and free of rubbish, however it is a building site and some temporary markings will occur, and it must be understood that we will be working with cement etc., so we require a position on site to clean our equipment as the setting time of the material means this cannot be done off site.
1B. Local government inspections required for steel & piering. If you are the owner applicant, this is your responsibility. Note: some Certifiers require an Engineer Certificate. It is advised to check conditions of approval.
Filtration final position to be confirmed as lines are run at this stage to final location.
1C. Concrete wash out is common to empty the hopper. Blobs are spread out as smaller rubble to handle when dry & disposed of in a suitable construction bin provided by owner.
2A. You are to provide correct size material to suit nominated coping width, allow for 50mm overhang into pool.
Oversize material will not be cut on site. Tiles must be on dot backing, not mesh. Tiles, glue & grout to be
supplied by customer.
2B. Sand & cement used to fill in pavers. Special coloured grouts to be supplied by client if desired. The coping
and waterline tiles must be finished and grouted with any expansion joints filled and all items cleaned off. External
surrounds laid by 3rd party must comply with adequate expansion joint and not butt up to pool structure.
3B. Electrician to earth the pool, install black light cable and any extensions if required, provide outdoor double power point 12 amp, occasional 3 phase power requirements for large heat pump or pool pumps.
The filtration will need to be in place and operational. We do provide precast slabs for the equipment to sit on however most Customers choose to provide a slab area for the filtration to on as part of their overall landscaping vision. You should allow 1100mm x 1100mm which is adequate for standard gear consisting of the filter, sanitiser and up to 2 pumps.Â
Order your permanent enclosure after equipment installation to ensure the right size.
4A. Pool to be earthed by your electrician. An outdoor waterproof power point to be supplied (12 amp double). Electrician to pull through black cable to connect the transformer. Lights and transformer to be on site.
5A. A compliant fence required to fill the pool with water. Pool filtration to be enclosed as per local government specs. Boundary fences to be raised to 1.8m if using as a pool safety barrier and items to be cleared of the 900mm non climb zone.
5B. If a permanent fence is erected, the temporary fence can now be dehired and removed from the site.
6A. The colour of your interior lining is as per contract. Any variations must be agreed in writing before materials arrive. If you would like to see images of your pool water colour in advance to make any changes.
The pool must now be clean and dewatered by you.
6B. Any of the lights or other internal fittings that need to be in screwed in place should be done in advance. All lights must be on site and provided to the render crew to render into place.
An uninterrupted supply of clean water and 240V power need to be available within 30 meters of the pool.
If your property has trees surrounding your pool that may drop leaves, flowers and nuts; please ensure these do not drop onto the pool floor before it is filled as they can cause tannin staining. We will leave the pool surface spotless but will not be responsible for organic droppings once we are finished and or leave the site. If necessary we suggest you cover the pool with a cheap tarp to keep leaves etc. off until the
pool is filled and until the surface is cured.
Cleaning of glass fencing, whilst we will do our utmost to work cleanly we do not accept liability, please ensure that the fence is completely covered/masked in advance to prevent any splashing onto the glass.
Note: While every effort will be made, and we do clean up after we finish, we are not commercial cleaners.
7. As the pool requires filling on the day immediately the render is finished. This means once your interior is done and pool filled the handover will be locked in. Your final payment will be due when the pool is full of water, prior to handover.
If there is anything preventing the immediate payment upon water filling please discuss this with your Rep. as its important for the water to not go stagnant once filled and this may happen is matters are left to be
addressed at this final stage.
8B. We require a skip bin for site clean up provided by you and will load it as part of our service.